Mechanical and Civil activities were completed by RHI on 10 May, 2017, and the Client PhosAgro-Cherepovets JSC, has issued mechanical completion certificate to RET. Also first Ammonia-drop milestone has been completed on 04 Jun, 2017 and Ammonia quality has reached %98.2 at 06 Jun, 2017.
As part of an EPC consortium, RET was the Mechanical & Civil General Contractor to PhosAgro-Cherepovets JSC, where the scope of work consisted 787,916 m3 earthwork, 50,443 m3 concrete works, 6,550 tons of steel erection, 13,596 tons equipment erection (including tank erection and heavy lifting), 440,690 WDI aboveground piping works, 871,742 m cable pulling works, 127 481 m2 insulation works and 271,964 m2 painting works for the PhosAgro Ammonia Plant capacity of 2,200 MTPD.
Project has been completed in 45,5 months. (From NTP up to Mechanical Completion