SEBRYAKOVCEMENT PLANT

In 2013, Renaissance successfully completed the Sebryakovcement plant project in the Volgograd Region of Russia. Sebryakovcement operates not only in Russia, but also in Kazakhstan and Azerbaijan. It continuously works on improving its production processes and enhancing its efficiency.

The daily production of the plant was increased to 3,575 tonnes. Renaissance’s scope of works included construction of temporary buildings, sixteen new buildings, earth works, infrastructure works, as well as all disassembly and modification works required for the existing structures.

Project Details

CONTRACT TYPE

Design-Build, Turnkey

SECTOR

Industrial Process

LOCATION

Volgograd, Russia

CONTRACT PERIOD

July 2011, August 2013

AREA

64600

CAPACITY

3575